Mookgophong Farm lines Assets Audit

Good Evening Mrs Mayor


Here is just a brief summary of what we have done over the last 2 days and our schedule for the following two weeks.


  • Total audits done - 367

  • Poles - 263

  • Meters - 59

  • Transformers - 41

  • Sectionallizers - 4


The audit project for the farm lines started with the Boekenhout line (Rooipad / Grootvallei) where this will be finished by the 19th of February 2020. There will be some outstanding audits, this is due to lack of access.


Herewith the schedule for the following 2 months:

19 Feb 2020 - 28 Feb 2020 Tobias line stretching along the R101:

Boekenhout line going towards Dinoyane Lodge / Visgat Line:


2 March 2020 - 15 April 2020

Rondalia Line stretching along the R520 towards Lekkerrus / Libbertas:

Constantia Line:


The red dots on the map below are all the assets that still need to be audited (as it currently stands). The black dots have already been done.


Kind Regards,

EMS Lingani JV project team